French EDF subsidiary makes huge spot-market error, faces bill of around €60 million

Electricite de Strasbourg, which is majority-owned by French giant EDF, mistakenly sold electricity with an output of 2.03 GW and 5.75 GW on the spot market, reports foreign news outlet Montel. Concerned about ensuring sufficient electricity supplies, the French transmission system operator sent an alert to neighboring countries.
In two separate transactions on 6 and 7 September this year, the company sold 2.03 GW and 5.75 GW, respectively (Note: no available sources have yet stated how many hours these amounts of power were sold for). A comparison with the Czech Temelín nuclear power plant, which has an output of 2.2 GW, illustrates just how large these amounts are.
The sale left the company short of electricity to meet its needs and exposed it to an imbalance. According to the Financial Times, this error cost the company €60 million in imbalance charges.
The situation prompted the French transmission system operator to send an emergency alert to neighboring countries. The alert was sent to the United Kingdom and Spain to prepare their transmission system operators for the possibility that large amounts of electricity might need to be imported into France during the hours in question. However, activating reserve generation was ultimately not necessary.
Translation disclaimer
This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.
The article continues for subscribers
Premium content
The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.
Best value: annual subscription
Monthly option 4 € / month
3.25 €/ month