Czech Temelín to extend both unit outages by a total of 50 days in 2017

Martin Voříšek
Martin Voříšek
15 September 2016, 12:51
Czech Temelín to extend both unit outages by a total of 50 days in 2017

Temelín Nuclear Power Plant this week extended its planned outages for 2017. The individual units at the newer of the Czech Republic’s two nuclear power plants will be shut down for 24 and 26 days longer, respectively, than originally planned. The reason is a broader scope of inspections and coordination with outages at Dukovany. According to the Temelín spokesperson, the longer outages in 2017 should be offset by shorter outages in subsequent years.

This is already the second extension of outages at Temelín this week. Following the extension of the ongoing outage at unit 2, the dates for 2017 were also revised at the beginning of this week:

FromToChange in daysChange in electricity generation
Unit 125. 8. 201710. 11. 201724 days0,6 TWh
Unit 212. 5. 20171. 8. 201726 days0,65 TWh

In total, the extension of outages at both units will amount to 50 days and, in terms of electricity generation, approximately 1,2 TWh.

Translation disclaimer

This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.

The article continues for subscribers

Premium content

The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.

You have read only 30% of the article — unlock the remaining 70% with a premium subscription.

Best value: annual subscription

Monthly option 4 € / month

3.25 €/ month

I already have a subscription