ČEZ to build wind farm in Germany, secures operating support

oEnergetice.cz, ČTK
oEnergetice.cz, ČTK
15 September 2022, 15:45
ČEZ to build wind farm in Germany, secures operating support

ČEZ Group will build a so-called wind farm with a capacity of 11.4 MW in Germany, with construction set to begin early next year. According to the schedule, the wind farm is expected to be ready for grid connection at the end of 2023. ČTK was informed today by ČEZ spokesperson Barbora Peterová. The Datteln project also secured operating support of 58.7 euros (about 1440 Kč) per megawatt-hour (MWh) in Germany’s auction for onshore wind farms. The company did not disclose the construction cost.

The wind farm, located north of Dortmund in the state of North Rhine-Westphalia, will consist of two turbines with rotor diameters of 149 metres, installed on 164-metre-high towers. The wind farm’s output will cover the annual consumption of about 6000 households.

By securing operating support, ČEZ will be guaranteed a tariff of 78 euros (about 1910 Kč) per MWh for 20 years from grid connection, with the tariff depending on the so-called correction factor. The correction factor varies according to the wind potential of the construction site and is used to adjust the guaranteed minimum generation price. „Simply put, projects near the sea have a lower correction factor; the poorer the site is in terms of wind conditions, the higher the operating support. Ideally, this system aims to ensure that wind farms are distributed evenly throughout Germany,“ said ČEZ board member Jan Kalina.

Translation disclaimer

This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.

The article continues for subscribers

Premium content

The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.

Best value: annual subscription

Monthly option 4 € / month

3.25 €/ month

I already have a subscription