Construction work begins on turbine hall of Turkey’s Akkuyu nuclear power plant Unit 4

Construction has begun on the foundation slab for the turbine hall of Unit 4 at Turkey’s Akkuyu nuclear power plant. The slab will be 7 metres thick and cover an area of 6000 square metres. Its construction will require approximately 17 500 cubic metres of concrete and 3500 tonnes of reinforcing steel.
The slab will be poured in 12 sections. Work on the first section, which will require 680 cubic metres of concrete, began on 27 May, according to Akkuyu Nuclear.
Before the slab could be poured, the foundation pit was prepared. This included building a concrete foundation bed using 38 000 cubic metres of concrete, installing waterproofing and reinforcing the foundation slab.
A stable foundation for the turbine generator
“The foundations being laid beneath the turbine hall are a complex structure capable of absorbing and evenly distributing loads during turbine operation,” said Anastasia Zoteeva, CEO of Akkuyu Nuclear, the chief designer and contractor for the four-unit Akkuyu nuclear power plant. “The foundations will be built in stages. Each stage is subject to strict requirements for concrete quality.”
Translation disclaimer
This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.
The article continues for subscribers
Premium content
The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.
You have read only 46% of the article — unlock the remaining 54% with a premium subscription.
Best value: annual subscription
Monthly option 4 € / month
3.25 €/ month