Pressure vessel for second reactor installed at Hinkley Point C nuclear power plant

Jiří Puchnar
Jiří Puchnar
10 June 2026, 13:25
Pressure vessel for second reactor installed at Hinkley Point C nuclear power plant

Construction of the UK’s Hinkley Point C nuclear power plant has reached another key milestone. The installation of the 500-tonne pressure vessel for the second EPR unit shows how EDF is drawing on experience from building the first unit to speed up construction both there and at the follow-on Sizewell C project. 

EDF Energy has completed the installation of the reactor pressure vessel for the second unit of the Hinkley Point C nuclear power plant in Somerset. The two-day operation began on Thursday morning and ended on Friday afternoon, when the vessel was set in place in the second unit’s reactor building.

Big Carl replaces temporary lifting system

Unlike the first unit, where the pressure vessel was installed using a large temporary lifting system, the second unit used the Big Carl crane. According to EDF, this approach saved space, time and money, and is another example of applying lessons learned during construction of the first unit.

Translation disclaimer

This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.

The article continues for subscribers

Premium content

The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.

You have read only 19% of the article — unlock the remaining 81% with a premium subscription.

Best value: annual subscription

Monthly option 4 € / month

3.25 €/ month

I already have a subscription