Removal of nuclear fuel debris from Fukushima plant to begin within 15 years

Removal of nuclear fuel debris from unit 3 of Japan’s Fukushima Daiichi nuclear power plant will begin no earlier than 2037. Engineers working at the site of the 2011 nuclear accident have presented two options for accessing the melted nuclear fuel debris. Together, units 1 and 2 contain approximately 880 tonnes of destroyed nuclear fuel. The complete decommissioning of the power plant is estimated to take 30-40 years.
Japanese energy company Tokyo Electric Power Company Holdings (TEPCO) has presented specific options for accessing the destroyed nuclear fuel in unit 3 of the Fukushima Daiichi nuclear power plant. It will begin removing this nuclear waste from unit 3 and estimates that preparatory work will take 12-15 years. The company had originally announced that the process would start in the early 2030s. As part of the preparations, TEPCO will have to build supporting infrastructure, particularly additional buildings to house the equipment that will remove material from the unit’s containment vessel.
Translation disclaimer
This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.
The article continues for subscribers
Premium content
The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.
You have read only 34% of the article — unlock the remaining 66% with a premium subscription.
Best value: annual subscription
Monthly option 4 € / month
3.25 €/ month