Strikes in France could delay the return to service of nuclear power plants with a capacity of up to 7.2 GW

Daniel Grecman
18 October 2022, 08:24
Strikes in France could delay the return to service of nuclear power plants with a capacity of up to 7.2 GW

Ongoing strikes in France will delay the return to service of up to 8 nuclear power plants with a total installed capacity of 7.2 GW, Montel reported, citing a statement by representatives of the country's largest energy union, FNME-CGT. Employees are on strike over growing dissatisfaction with their pay. An EDF spokesperson told Reuters on Saturday that 6 units had so far been affected by the strikes.

Strikes will extend outages

According to an EDF spokesperson, strikes over higher wages have so far delayed the return of 6 units from outages by one day or more. As union representative Sébastien Menesplier points out, each additional day an individual unit is offline typically costs EDF around 1 million EUR.

“The action [strikes] will affect the company's finances: a day's outage at a unit is usually worth 1 million EUR. At current prices, however, it is 5x to 10x more,” Menesplier said.
Translation disclaimer

This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.

The article continues for subscribers

Premium content

The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.

You have read only 37% of the article — unlock the remaining 63% with a premium subscription.

Best value: annual subscription

Monthly option 4 € / month

3.25 €/ month

I already have a subscription