The Queensland state government has halted the planned Moonlight Range wind farm, which is set to have nearly 90 turbines. The government moved to stop the project after receiving hundreds of submissions calling for its approval to be reconsidered. Wind farms have also faced public opposition in Europe, although in recent months it is mainly offshore wind farm projects that have been halted because they are unprofitable.

The Queensland government received more than 550 submissions, according to Argus, including 142 from local residents. Around 85% of these submissions called for the approval of the Moonlight Range project to be reviewed. The wind farm, planned to have 88 turbines, would have an installed capacity of 450 MW and include battery storage. The project developer, Greenleaf Renewables, had initially planned to begin construction next year.

The project was originally approved by a government agency last December, but the situation is changing following the new government’s arrival. The governing Liberal National Party promised in January to tighten regulation of wind farms, according to Argus. This is set to include involving local communities in the consultation process for new projects, leading to delays in their development.

The previous government passed new legislation last April that includes a target of cutting emissions by 75% by 2035 and achieving net-zero emissions by 2050. The new government is expected to present its plans for net-zero emissions and energy sector development by the end of this year.