ČEPS to double the V403 line in the Olomouc, Zlín and Moravian-Silesian regions of Czechia

ČEPS has launched an investment project to double the V403 line, which runs through the Olomouc, Zlín and Moravian-Silesian regions. The aim is to increase the line’s transmission capacity and strengthen the security and reliability of electricity supplies in these regions.
The “V403/803 – line doubling” project will be carried out along the section between the Prosenice substation in the Olomouc Region and the Nošovice substation in the Moravian-Silesian Region. The new line will be routed entirely along the existing overhead line route, which is 79.5 km long.
“Doubling the original V403 line, which was already nearing the end of its service life, will increase its transmission capacity while also improving the security and reliability of electricity transmission in the Olomouc, Zlín and Moravian-Silesian regions,” said Karel Slončík, a member of ČEPS’s board of directors responsible for managing the Transmission System Management, Operation and Maintenance division.
As part of the doubling of the V403 line, built in 1959, all towers and their foundations, phase conductors, earth wires and insulator strings will be replaced. Once completed, V403/803 will comprise 160 towers of the Dunaj and Soudek types.
Translation disclaimer
This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.
The article continues for subscribers
Premium content
The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.
Best value: annual subscription
Monthly option 4 € / month
3.25 €/ month