Czechia's largest battery, being built in Ostrava-Vítkovice, will be ready by year-end

oEnergetice.cz, ČTK
oEnergetice.cz, ČTK
11 June 2023, 10:23
Czechia's largest battery, being built in Ostrava-Vítkovice, will be ready by year-end

The largest battery storage system in the Czech Republic, which ČEZ Group is building in Ostrava-Vítkovice, will be completed by the end of this year. Company spokesperson Vladislav Sobol told CTK today. The battery, which is as large as a family home, will have a capacity of almost ten megawatt-hours of energy—three times that of ČEZ's current largest battery in Tušimice in the Chomutov region.

The project is expected to cost around 100 million crowns. ČEZ aims to build new energy storage facilities with a capacity of 300 megawatts by 2030. The Ostrava battery is being built at the site of ČEZ Energetické služby in Ostrava-Vítkovice. Following demolition, the main construction work has now begun and is expected to be completed by the end of the year.

“The main construction work is now in full swing. It involves building retention tanks and foundations, creating new paved areas and relocating power cables from the decommissioned energy duct,” said Rostislav Díža, director of ČEZ Energetické služby.
Translation disclaimer

This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.

The article continues for subscribers

Premium content

The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.

You have read only 37% of the article — unlock the remaining 63% with a premium subscription.

Best value: annual subscription

Monthly option 4 € / month

3.25 €/ month

I already have a subscription