Dismantling of nuclear reactors at Jaslovské Bohunice completed

Jiří Puchnar
Jiří Puchnar
6 August 2022, 12:49
Dismantling of nuclear reactors at Jaslovské Bohunice completed

Both VVER 440 V-230 reactors at Jaslovské Bohunice have been decommissioned and dismantled on site. This is the first complete dismantling of this type of reactor, the European Bank for Reconstruction and Development (EBRD) said.

The Bohunice International Decommissioning Support Fund had €650 million as of mid-2018, with contributions from the European Commission, Austria, Denmark, France, Ireland, the Netherlands, Spain, Switzerland and the United Kingdom. The fund is managed by the European Bank for Reconstruction and Development (EBRD).

Total decommissioning cost: 1,237 bn €

The EBRD said that the work, which involved completely dismantling the reactors and decontaminating their components for safe disposal or recycling, “was completed on schedule and within the expected budget”. The project will provide valuable experience and expertise for decommissioning other nuclear power plants around the world.

Preparations for decommissioning the two V1 reactors began in 2012, after they were shut down in 2005 and 2008 (on 31 December in each case). The remaining equipment and systems at the site are scheduled to be dismantled and processed by 2025. The power plant buildings will then be demolished and the site prepared for redevelopment by 2027.

Translation disclaimer

This article is a machine translation of the Czech original and has not yet been fully reviewed. In case of any doubt, please refer to the Czech version.

The article continues for subscribers

Premium content

The rest of this article is available to premium subscribers only. Get access to all premium articles on oEnergetice.cz.

You have read only 47% of the article — unlock the remaining 53% with a premium subscription.

Best value: annual subscription

Monthly option 4 € / month

3.25 €/ month

I already have a subscription